Skip to Main Content
Skip to Navigation

Service Area Project Locations

Service Area Redesign and Redevelopment Project
Name Location Milepost Opening Date Level Sq. Feet
ArdsleyNorthbound, Exit 6A (Yonkers Toll Gantry) & Exit 7 (Ardsley)6June 8, 20232A14,654
SloatsburgNorthbound, Exit 15A (Suffern Rt. 17N) & Exit 16 (Woodbury Toll Gantry)33September 9, 2024331,428
PlattekillNorthbound, Exit 17 (Newburgh I-84) & Exit 18 (New Paltz)65May 3, 2023320,145
MaldenNorthbound, Exit 20 (Saugerties) & Exit 21 (Catskill)103October 9, 20242A18,220
New BaltimoreNorthbound & Southbound, Exit 21B (Coxsackie) & Exit 21A (Berkshire Section/to Mass Pike)127June 29, 2023320,145
PattersonvilleWestbound, Exit 26 (Schenectady West) & Exit 27 (Amsterdam)168September 24, 20242B16,240
IroquoisWestbound, Exit 29 (Canajoharie) & Exit 29A (Little Falls)210February 14, 20232A14,654
SchuylerWestbound, Exit 30 (Herkimer) & Exit 31 (Utica)227October 30, 202313,896
ChittenangoWestbound, Exit 34 (Canastota) & Exit 34A (Syracuse I-481)266September 12, 202225,742
WarnersWestbound, Exit 39 (Syracuse West) & Exit 40 (Weedsport)292March 25, 20242A14,654
Junius PondsWestbound, Exit 41 (Waterloo) & Exit 42 (Geneva)324October 6, 202225,742
SenecaWestbound, Exit 44 (Canandaigua) & Exit 45 (Rochester I-490)350September 8, 202325,742
OntarioWestbound, Exit 46 (Rochester) & Exit 47 (Leroy)376October 2, 20242A18,220
ClarenceWestbound, Exit 48A (Pembroke) & Exit 49 (Depew)412June 28, 20232B14,654
AngolaEastbound & Westbound, Exit 57A (Eden-Angola) & Exit 58 (Silver Creek)447Quarter 1 2025320,145
PembrokeEastbound, Exit 48A (Pembroke) & Exit 48 (Batavia)397July 13, 20233B20,145
ScottsvilleEastbound, Exit 47 (Leroy) & Exit 46 (Rochester)366June 25, 202425,742
Clifton SpringsEastbound, Exit 43 (Manchester) & Exit 42 (Geneva)337March 28, 2023320,145
Port ByronEastbound, Exit 41 (Waterloo) & Exit 40 (Weedsport)310February 19, 202425,742
DeWittEastbound, Exit 36 (Syracuse I-81) & Exit 35 (Syracuse East)280September 17, 202413,896
OneidaEastbound, Exit 33 (Verona-Rome) & Exit 32 (Westmoreland-Rome)244January 10, 20242A14,654
Indian CastleEastbound, Exit 29A (Little Falls) & Exit 29 (Canajoharie)210August 26, 202225,742
MohawkEastbound, Exit 27 (Amsterdam) & Exit 26 (Schenectady West)172Quarter 1 202525,742
GuilderlandEastbound, Exit 25 (Schenectady East) & Exit 24 (Albany Northway)153May 8, 202425,742
UlsterSouthbound, Exit 20 (Saugerties) & Exit 19 (Kingston)96November 6, 20242B14,654
ModenaSouthbound, Exit 18 (New Paltz) & Exit 17 (Newburgh I-84)66Quarter 4 2025320,145
RamapoSouthbound, Exit 16 (Woodbury Toll Gantry) & Exit 15A (Suffern Rt. 17N)33June 26, 2024320,145

 

Service Areas

*Fuel services will remain available during construction at all Service Areas