For The Week Starting Monday 07/22/2024
Rochester Region
Between Exits | Work Description | Lane Closure Information | Likely Impacts | Comments |
---|---|---|---|---|
43 & 42 | Road Work | East: Right lane, MON-TUE 3AM-7AM | Minimal | None |
45 & 46 | Bridge Construction | West: Left shoulder, Monday 7/22/24 7:00am - 4:00pm. Tuesday 7/23/24 7:00am - 4:00pm. Wednesday 7/24/24 7:00am - 4:00pm. Thursday 7/25/24 7:00am - 4:00pm. Friday 7/26/24 7:00am - 4:00pm. | Minor | None |
45 & 47 | Paving | West: Left lane, Monday 7/22/24 7:00pm -through- 6:00am Tuesday 7/23/24. Tuesday 7/23/24 6:00pm -through- 6:00am Wednesday 7/24/24. West: Right lane, Wednesday 7/24/24 6:00pm -through- 6:00am Thursday 7/25/24. Thursday 7/25/24 7:00pm -through- 6:00am Friday 7/26/24. Friday 7/26/24 8:00pm -through- 6:00am Saturday 7/27/24. | Minimal | None |
45 & 47 | Bridge Construction | West: Right shoulder, Long Term Closure Sunday 7/21/24 -through- Saturday 7/27/24. | Minor | None |
47 & 46 | Bridge Construction | East: Right shoulder, Long Term Closure Sunday 7/21/24 -through- Saturday 7/27/24. | Minor | None |
47 & 45 | Paving | East: Left lane, Monday 7/22/24 6:00pm -through- 6:00am Tuesday 7/23/24. Tuesday 7/23/24 6:00pm -through- 6:00am Wednesday 7/24/24. East: Right lane, Wednesday 7/24/24 6:00pm -through- 6:00am Thursday 7/25/24. Thursday 7/25/24 7:00pm -through- 6:00am Friday 7/26/24. Friday 7/26/24 8:00pm -through- 6:00am Saturday 7/27/24. | Minimal | None |
For The Week Starting Monday 07/29/2024
Rochester Region
Between Exits | Work Description | Lane Closure Information | Likely Impacts | Comments |
---|---|---|---|---|
45 & 46 | Bridge Construction | West: Left shoulder, Monday 7/29/24 7:00am - 4:00pm. Tuesday 7/30/24 7:00am - 4:00pm. Wednesday 7/31/24 7:00am - 4:00pm. Thursday 8/1/24 7:00am - 4:00pm. Friday 8/2/24 7:00am - 4:00pm. | Minor | None |
45 & 47 | Paving | West: Left lane, Monday 7/29/24 7:00pm -through- 6:00am Tuesday 7/30/24. Tuesday 7/30/24 6:00pm -through- 6:00am Wednesday 7/31/24. West: Right lane, Wednesday 7/31/24 6:00pm -through- 6:00am Thursday 8/1/24. Thursday 8/1/24 7:00pm -through- 6:00am Friday 8/2/24. Friday 8/2/24 8:00pm -through- 6:00am Saturday 8/3/24. | Minimal | None |
45 & 47 | Bridge Construction | West: Right shoulder, Long Term Closure Sunday 7/28/24 -through- Saturday 8/3/24. | Minor | None |
47 & 46 | Bridge Construction | East: Right shoulder, Long Term Closure Sunday 7/28/24 -through- Saturday 8/3/24. | Minor | None |
47 & 45 | Paving | East: Right lane, Wednesday 7/31/24 6:00pm -through- 6:00am Thursday 8/1/24. Thursday 8/1/24 7:00pm -through- 6:00am Friday 8/2/24. Friday 8/2/24 8:00pm -through- 6:00am Saturday 8/3/24. East: Left lane, Monday 7/29/24 6:00pm -through- 6:00am Tuesday 7/30/24. Tuesday 7/30/24 6:00pm -through- 6:00am Wednesday 7/31/24. | Minimal | None |